Dept. of Trans. PROGRESS Serial No. Contract No. 12-206-15-02 10-0M8004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 37% 22% 10-STA-99-R0.0/R24.7 Federal Project: ACNH-P099(549) Progress payment No. 04 Payment period ending: 07-20-12 MYERS AND SONS CONSTRUCTION LP 2554 MILLCREEK DRIVE SACRAMENTO CA 95833 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 21,001,951.54 9,717,055.40 2.a. Extra Work 12,522.75 2,120.75 b. Adjustment Comp. 3. Materials on Hand 252,375.89 -38,654.79 4. Earned Subject to Retention 21,266,850.18 9,680,521.36 5. Mobilization 6,935,000.00 1,460,000.00 6. Total Work Completed 27,949,474.29 7. Deductions -213,600.00 -210,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 27,988,250.18 10,930,521.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,930,521.36