Dept. of Trans. PROGRESS Serial No. Contract No. 12-331-09-22 10-0M8004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 81% 74% 10-STA-99-R0.0/R24.7 Federal Project: ACNH-P099(549) Progress payment No. 08 Payment period ending: 11-20-12 MYERS AND SONS CONSTRUCTION LP 2554 MILLCREEK DRIVE SACRAMENTO CA 95833 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 56,741,694.41 3,934,382.32 2.a. Extra Work 327,300.67 495.07 b. Adjustment Comp. 391,033.14 0.00 3. Materials on Hand 347,526.58 -50,429.23 4. Earned Subject to Retention 57,807,554.80 3,884,448.16 5. Mobilization 7,300,000.00 0.00 6. Total Work Completed 64,760,028.22 7. Deductions -74,740.00 -20,500.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 65,032,814.80 3,863,948.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,863,948.16