Dept. of Trans. PROGRESS Serial No. Contract No. 13-143-14-28 10-0M8004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 100% 10-STA-99-R0.0/R24.7 Federal Project: ACNH-P099(549) Progress payment No. 14 Payment period ending: 05-20-13 MYERS AND SONS CONSTRUCTION LP 2554 MILLCREEK DRIVE SACRAMENTO CA 95833 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 67,613,655.63 900,964.80 2.a. Extra Work 758,963.47 254,420.90 b. Adjustment Comp. 277,129.01 0.00 3. Materials on Hand 50,000.00 -50,000.00 4. Earned Subject to Retention 68,699,748.11 1,105,385.70 5. Mobilization 7,300,000.00 0.00 6. Total Work Completed 75,949,748.11 7. Deductions -146,680.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 75,853,068.11 1,095,385.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,095,385.70