Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 09-279-08-34 10-0N1704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 10-MER-99-18.5/ .0 Federal Project: NONE Progress payment No. 05 Payment period ending: 10-01-09 JEFFCO PAINTING AND COATING INC P O BOX 1888 VALLEJO CA 94590 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 413,710.00 45,814.00 2.a. Extra Work 106,986.00 56,986.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 520,696.00 102,800.00 5. Mobilization 45,000.00 0.00 6. Total Work Completed 565,696.00 7. Deductions -6,000.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 559,696.00 97,800.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 97,800.00