Dept. of Trans. PROGRESS Serial No. Contract No. 09-141-10-32 10-0N2504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 68% 69% 10-SJ-5-25.6/26.1 Federal Project: NONE Progress payment No. 06 Payment period ending: 05-20-09 PENHALL COMPANY 13750 CATALINA STREET SAN LEANDRO CA 94577 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 749,127.81 237,618.65 2.a. Extra Work 29,263.19 4,210.45 b. Adjustment Comp. 3. Materials on Hand 45,290.20 -12,757.71 4. Earned Subject to Retention 823,681.20 229,071.39 5. Mobilization 120,000.00 6,000.00 6. Total Work Completed 898,391.00 7. Deductions 8. a.Contract Retentions -41,184.06 -11,453.57 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 902,497.14 223,617.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 223,617.82