Dept. of Trans. PROGRESS Serial No. Contract No. 08-171-10-22 10-0N5804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 89% 40% 10-SJ-580-9.0/15.3 Federal Project: NONE Progress payment No. 02 Payment period ending: 06-20-08 TOM MAYO CONSTRUCTION INC 4735 E FREMONT ST STOCKTON CA 95215 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 979,567.24 697,092.01 2.a. Extra Work 515,829.60 515,829.60 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,495,396.84 1,212,921.61 5. Mobilization 6. Total Work Completed 1,495,396.84 7. Deductions 8. a.Contract Retentions -74,769.84 -51,574.18 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,420,627.00 1,161,347.43 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,161,347.43