Dept. of Trans. PROGRESS Serial No. Contract No. 12-297-10-06 10-0P2604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 94% 10-TUO-49-R12.2/12.0 Federal Project: NONE Progress payment No. 05 Payment period ending: 10-20-12 MCI ENGINEERING 7207 MURRAY DRIVE STOCKTON CA 95210 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 478,808.15 4,567.00 2.a. Extra Work 52,569.63 52,569.63 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 531,377.78 57,136.63 5. Mobilization 6. Total Work Completed 531,377.78 7. Deductions -15,000.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 516,377.78 52,136.63 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 52,136.63