Dept. of Trans. PROGRESS Serial No. Contract No. 08-295-08-40 10-0P4404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 79% 100% 10-MPA-140-42.3 Federal Project: NONE Progress payment No. 24 Payment period ending: 10-20-08 TEICHERT CONSTRUCTION P. O. BOX 3367 TURLOCK, CA 95381 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2.a. Extra Work 11,051,237.76 347,231.32 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 11,051,237.76 347,231.32 5. Mobilization 6. Total Work Completed 11,051,237.76 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,041,237.76 337,231.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 337,231.32