Dept. of Trans. PROGRESS Serial No. Contract No. 19-234-10-06 10-0P5504 PROGRESS PAYMENT VOUCHER %complete: %time: 32% 24% Location: Federal Project: 10-MER-5-13.5/19.2 B1ST-000C(488) 10-MER-152-18.5 10-STA-5-5.8/7.2 Progress payment No. 003 Payment period ending: 08-20-19 BRIDGEWAY CIVIL CONSTRUCTORS INC 4950 ALLISON PKWY #A VACAVILLE CA 95688 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 566,610.10 468,451.60 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 335,786.62 136,157.37 4. Earned Subject to Retention 902,396.72 604,608.97 5. Mobilization 217,455.00 45,780.00 6. Total Work Completed 784,065.10 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,119,851.72 650,388.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 650,388.97