Dept. of Trans. PROGRESS Serial No. Contract No. 22-115-07-33 10-0Q1214 PROGRESS PAYMENT VOUCHER %complete: %time: 87% 98% Location: Federal Project: 10-MER-99-28.2/R37.3 EPNH-P099(639) Progress payment No. 026 Payment period ending: 04-20-22 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 27,126,589.53 657,369.92 2. a. Extra Work 311,502.95 28,606.55 b. Adustment Comp. -17,818.14 -20,768.14 3. Materials on Hand 69,280.75 -77,512.73 4. Earned Subject to Retention 27,489,555.09 587,695.60 5. Mobilization 620,000.00 0.00 6. Total Work Completed 28,040,274.34 7. Deductions -59,045.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 28,050,510.09 587,695.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 587,695.60