Dept. of Trans. PROGRESS Serial No. Contract No. 17-233-14-36 10-0Q1604 PROGRESS PAYMENT VOUCHER %complete: %time: 74% 82% Location: Federal Project: 10-SJ-99-0.0/5.7 ACNH-PP09-9(602) Progress payment No. 004 Payment period ending: 08-20-17 TEICHERT CONSTRUCTION PO BOX 13557 SACRAMENTO CA 95853 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,579,548.78 2,238,605.06 2. a. Extra Work b. Adustment Comp. -65,000.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 5,514,548.78 2,238,605.06 5. Mobilization 825,200.00 41,260.00 6. Total Work Completed 6,339,748.78 7. Deductions -47,386.13 532,766.11 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 6,292,362.65 2,812,631.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,812,631.17