Dept. of Trans. PROGRESS Serial No. Contract No. 11-263-08-35 10-0S1704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 40% 76% 10-ALP-88-5.3/5.3 Federal Project: NH-P088(54) Progress payment No. 02 Payment period ending: 09-20-11 FORD CONSTRUCTION COMPANY INC 639 E LOCKEFORD STREET LODI CA 95240 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 737,819.40 543,136.80 2.a. Extra Work 24,918.67 17,277.92 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 762,738.07 560,414.72 5. Mobilization 50,350.00 10,600.00 6. Total Work Completed 813,088.07 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 813,088.07 571,014.72 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 571,014.72