Dept. of Trans. PROGRESS Serial No. Contract No. 12-355-10-38 10-0S2404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 47% 43% 10-TUO-108-58.8/58.8 Federal Project: NONE Progress payment No. 06 Payment period ending: 12-20-12 C W FOX CONSTRUCTION INC 2701 SECRET LAKE TRAIL COOL CA 95614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 308,686.32 0.00 2.a. Extra Work 31,793.79 10,325.12 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 340,480.11 10,325.12 5. Mobilization 37,966.03 0.00 6. Total Work Completed 378,446.14 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 378,446.14 10,325.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,325.12