Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 09-251-08-46 10-0S2804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 10-SJ-5-R13.8/25.4 Federal Project: NONE Progress payment No. 04 Payment period ending: 08-25-09 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,866,709.88 105,686.60 2.a. Extra Work 70,753.40 70,753.40 b. Adjustment Comp. -133,549.34 -133,549.34 3. Materials on Hand 4. Earned Subject to Retention 2,803,913.94 42,890.66 5. Mobilization 6. Total Work Completed 2,803,913.94 7. Deductions -20,000.00 -20,000.00 8. a.Contract Retentions -138,051.16 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 138,051.16 138,051.16 9. Total pay to Contractor 2,783,913.94 160,941.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 160,941.82