Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 22-347-09-46 10-0S7404 PROGRESS PAYMENT VOUCHER %complete: %time: 81% 100% Location: Federal Project: 10-SJ-88-13.7/14.0 NONE 10-ALP-88-0.2/2.4 Progress payment No. 009 Payment period ending: 11-20-22 EVERLEVEL HOLDINGS LLC 5877 PINE AVE #120 CHINO HILLS CA 91709 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,621,415.65 34,000.00 2. a. Extra Work 341,356.31 262,966.05 b. Adustment Comp. 3. Materials on Hand 100,000.00 -100,000.00 4. Earned Subject to Retention 3,062,771.96 196,966.05 5. Mobilization 380,000.00 0.00 6. Total Work Completed 3,342,771.96 7. Deductions -7,909.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,434,862.96 196,966.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 196,966.05