Dept. of Trans. PROGRESS Serial No. Contract No. 14-168-14-27 10-0T1604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 35% 46% 10-SJ-26-18.5/19.0 Federal Project: HSST-P026(28) Progress payment No. 02 Payment period ending: 06-20-14 CHESTER BROSS CONSTRUCTION 39 CALIFORNIA ST PMB 118 VALLEY SPRINGS CA 95252 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 593,212.95 193,469.95 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 593,212.95 193,469.95 5. Mobilization 151,442.35 31,882.60 6. Total Work Completed 744,655.30 7. Deductions -1,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 743,655.30 225,352.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 225,352.55