Dept. of Trans. PROGRESS Serial No. Contract No. 10-294-14-37 10-0T4204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 85% 100% 10-MER-5 Federal Project: NONE Progress payment No. 02 Payment period ending: 10-20-10 VICTORY ENGINEERS, INC. 10266 HIGHWAY 41 MADERA, CA 93636 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 262,026.58 203,889.94 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 262,026.58 203,889.94 5. Mobilization 8,251.84 412.59 6. Total Work Completed 270,278.42 7. Deductions -13,300.00 -13,300.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 256,978.42 191,002.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 191,002.53