Dept. of Trans. PROGRESS Serial No. Contract No. 23-331-10-26 10-0T6804 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 90% Location: Federal Project: 10-MER-5-6.3 ACNH-X047(13) 10-MER-152-11.3 Progress payment No. 008 Payment period ending: 11-20-23 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,537,880.86 249,751.57 2. a. Extra Work 82,051.66 28,963.07 b. Adustment Comp. -7,500.00 -7,500.00 3. Materials on Hand 0.00 -29,957.11 4. Earned Subject to Retention 2,612,432.52 241,257.53 5. Mobilization 130,000.00 0.00 6. Total Work Completed 2,742,432.52 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,742,432.52 241,257.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 241,257.53