Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 23-363-09-51 10-0T6804 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 10-MER-5-6.3 ACNH-X047(13) 10-MER-152-11.3 Progress payment No. 009 Payment period ending: 12-11-23 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,651,170.84 113,289.98 2. a. Extra Work 82,051.66 0.00 b. Adustment Comp. -7,500.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,725,722.50 113,289.98 5. Mobilization 130,000.00 0.00 6. Total Work Completed 2,855,722.50 7. Deductions -30,000.00 -30,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,825,722.50 83,289.98 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 83,289.98