Dept. of Trans. PROGRESS Serial No. Contract No. 17-143-11-01 10-0T7804 PROGRESS PAYMENT VOUCHER %complete: %time: 9% 17% Location: Federal Project: 10-STA-132-1.1/1.8 ACHS-NHPP-1(320) Progress payment No. 001 Payment period ending: 05-20-17 GRANITE CONSTRUCTION COMPANY 2716 GRANITE CT FRESNO CA 93706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 114,140.00 114,140.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 114,140.00 114,140.00 5. Mobilization 80,000.00 80,000.00 6. Total Work Completed 194,140.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 194,140.00 194,140.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 194,140.00