Dept. of Trans. PROGRESS Serial No. Contract No. 17-360-11-17 10-0U2904 PROGRESS PAYMENT VOUCHER %complete: %time: 58% 58% Location: Federal Project: 10-MER-165-35.6/36.1 ACHS-STPP-1(651) Progress payment No. 004 Payment period ending: 12-20-17 TEICHERT CONSTRUCTION PO BOX 13557 SACRAMENTO CA 95853 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 707,585.50 352,976.65 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 707,585.50 352,976.65 5. Mobilization 136,881.50 6,844.08 6. Total Work Completed 844,467.00 7. Deductions 0.00 1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 844,467.00 360,820.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 360,820.73