Dept. of Trans. PROGRESS Serial No. Contract No. 18-330-10-01 10-0U5204 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 100% Location: Federal Project: 10-MER-59-12.8/13.5 HSST-P059(74) Progress payment No. 003 Payment period ending: 11-20-18 AGEE CONSTRUCTION CORPORATION PO BOX 629 CLOVIS CA 93613 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 809,019.79 392,617.99 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 809,019.79 392,617.99 5. Mobilization 90,000.00 4,500.00 6. Total Work Completed 899,019.79 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 889,019.79 387,117.99 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 387,117.99