Dept. of Trans. PROGRESS Serial No. Contract No. 12-237-09-10 10-0U5804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 87% 22% 10-SJ-5-R12.4/39.6 Federal Project: NONE Progress payment No. 10 Payment period ending: 08-20-12 MYERS AND SONS CONSTRUCTION LP 2554 MILLCREEK DRIVE SACRAMENTO CA 95833 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,196,504.00 -10,694.00 2.a. Extra Work 599,003.27 545,473.17 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 2,795,507.27 534,779.17 5. Mobilization 285,000.00 0.00 6. Total Work Completed 3,080,507.27 7. Deductions -32,147.75 -9,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,048,359.52 525,779.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 525,779.17