Dept. of Trans. PROGRESS Serial No. Contract No. 11-201-10-26 10-0U5904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 48% 100% 10-SJ-132-L0.7/ .0 Federal Project: NONE Progress payment No. 02 Payment period ending: 07-20-11 JEFFCO PAINTING & COATING INC PO BOX 1888 VALLEJO CA 94590 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 259,288.20 124,196.90 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 259,288.20 124,196.90 5. Mobilization 29,450.00 0.00 6. Total Work Completed 288,738.20 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 278,738.20 114,196.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 114,196.90