Dept. of Trans. PROGRESS Serial No. Contract No. 12-139-13-02 10-0U6004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 34% 59% 10-SJ-4-4.4/ .0 Federal Project: NONE Progress payment No. 07 Payment period ending: 05-20-12 MURPHY INDUSTRIAL COATINGS INC 2704 GUNDRY AVENUE SIGNAL HILL CA 90755 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 777,957.73 209,395.15 2.a. Extra Work 8,443.83 1,241.46 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 786,401.56 210,636.61 5. Mobilization 95,000.00 0.00 6. Total Work Completed 881,401.56 7. Deductions -5,000.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 876,401.56 205,636.61 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 205,636.61