Dept. of Trans. PROGRESS Serial No. Contract No. 11-264-14-12 10-0U8404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 27% 28% 10-SJ-4-29.5/38.1 Federal Project: ACST-PP00(414) Progress payment No. 01 Payment period ending: 09-20-11 GEORGE REED INC P O BOX 4760 MODESTO CA 95354 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 405,583.97 405,583.97 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 405,583.97 405,583.97 5. Mobilization 6. Total Work Completed 405,583.97 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 405,583.97 405,583.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 405,583.97