Dept. of Trans. SEMI-FINAL Serial No. Contract No. 12-104-08-43 10-0U8804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 10-TUO-120-R38.2/R52.7 Federal Project: ACNH-P120(52) Progress payment No. 06 Payment period ending: 11-29-11 GEORGE REED INC P O BOX 4760 MODESTO, CA 95352 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,219,519.03 0.00 2.a. Extra Work 12,799.66 0.00 b. Adjustment Comp. 56,741.19 -2,974.01 3. Materials on Hand 4. Earned Subject to Retention 2,289,059.88 -2,974.01 5. Mobilization 6. Total Work Completed 2,289,059.88 7. Deductions -2,000.00 8,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,287,059.88 5,025.99 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,025.99