Dept. of Trans. PROGRESS Serial No. Contract No. 19-295-09-22 10-0V1104 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 77% Location: Federal Project: 10-STA-99-R18.0/R21.2 HSNH-P099(633) Progress payment No. 008 Payment period ending: 10-20-19 TEICHERT CONSTRUCTION PO BOX 13557 SACRAMENTO CA 95853 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,884,009.33 256,120.42 2. a. Extra Work 332,877.90 1,100.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 7,216,887.23 257,220.42 5. Mobilization 837,500.00 0.00 6. Total Work Completed 8,054,387.23 7. Deductions -51,000.00 -50,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 8,003,387.23 207,220.42 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 207,220.42