Dept. of Trans. PROGRESS Serial No. Contract No. 17-275-15-51 10-0V3004 PROGRESS PAYMENT VOUCHER %complete: %time: 64% 71% Location: Federal Project: 10-CAL-4-29.6 ACST-P000-C(441) 10-MPA-49-18.5/18.7 10-MPA-140-21.8 Progress payment No. 003 Payment period ending: 09-20-17 GEORGE REED INC 140 EMPIRE AVENUE MODESTO CA 95354 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 799,942.50 418,057.50 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 799,942.50 418,057.50 5. Mobilization 120,000.00 6,000.00 6. Total Work Completed 919,942.50 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 919,942.50 424,057.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 424,057.50