Dept. of Trans. PROGRESS Serial No. Contract No. 25-055-11-55 10-0V4804 PROGRESS PAYMENT VOUCHER %complete: %time: 0% 1% Location: Federal Project: 10-CAL-26-21.8/30.3 ACST-S026(32) Progress payment No. 001 Payment period ending: 02-20-25 VIKING CONSTRUCTION CO INC PO BOX 1508 RANCHO CORDOVA CA 95741-1508 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 241,895.54 241,895.54 4. Earned Subject to Retention 241,895.54 241,895.54 5. Mobilization 6. Total Work Completed 0.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 241,895.54 241,895.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 241,895.54