Dept. of Trans. PROGRESS Serial No. Contract No. 25-143-09-00 10-0V4804 PROGRESS PAYMENT VOUCHER %complete: %time: 28% 23% Location: Federal Project: 10-CAL-26-21.8/30.3 ACST-S026(32) Progress payment No. 004 Payment period ending: 05-20-25 VIKING CONSTRUCTION CO INC PO BOX 1508 RANCHO CORDOVA CA 95741-1508 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,330,666.58 768,933.58 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 151,982.09 -89,913.45 4. Earned Subject to Retention 1,482,648.67 679,020.13 5. Mobilization 683,050.00 143,800.00 6. Total Work Completed 2,013,716.58 7. Deductions -15,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,150,698.67 812,820.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 812,820.13