Dept. of Trans. PROGRESS Serial No. Contract No. 25-169-11-07 10-0V4804 PROGRESS PAYMENT VOUCHER %complete: %time: 35% 36% Location: Federal Project: 10-CAL-26-21.8/30.3 ACST-S026(32) Progress payment No. 005 Payment period ending: 06-20-25 VIKING CONSTRUCTION CO INC PO BOX 1508 RANCHO CORDOVA CA 95741-1508 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,839,493.30 508,826.72 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 95,880.21 -56,101.88 4. Earned Subject to Retention 1,935,373.51 452,724.84 5. Mobilization 683,050.00 0.00 6. Total Work Completed 2,522,543.30 7. Deductions -142,206.68 -127,206.68 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,476,216.83 325,518.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 325,518.16