Dept. of Trans. PROGRESS Serial No. Contract No. 25-203-10-56 10-0V4804 PROGRESS PAYMENT VOUCHER %complete: %time: 40% 46% Location: Federal Project: 10-CAL-26-21.8/30.3 ACST-S026(32) Progress payment No. 006 Payment period ending: 07-20-25 VIKING CONSTRUCTION CO INC PO BOX 1508 RANCHO CORDOVA CA 95741-1508 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,242,549.87 403,056.57 2. a. Extra Work 674.63 674.63 b. Adustment Comp. 3. Materials on Hand 0.00 -95,880.21 4. Earned Subject to Retention 2,243,224.50 307,850.99 5. Mobilization 683,050.00 0.00 6. Total Work Completed 2,926,274.50 7. Deductions -282,206.68 -140,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,644,067.82 167,850.99 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 167,850.99