Dept. of Trans. SEMI-FINAL Serial No. Contract No. 12-277-08-46 10-0V8804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 10-STA-33-1.6/12.6 Federal Project: NONE Progress payment No. 03 Payment period ending: 09-06-12 TEICHERT CONSTRUCTION P O BOX 1118 STOCKTON CA 95206 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,715,421.79 75.75 2.a. Extra Work 17,643.99 1,981.59 b. Adjustment Comp. -16,204.74 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,716,861.04 2,057.34 5. Mobilization 6. Total Work Completed 1,716,861.04 7. Deductions 0.00 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,716,861.04 12,057.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 12,057.34