Dept. of Trans. FINAL Serial No. Contract No. 12-299-09-08 10-0V8804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 10-STA-33-1.6/12.6 Federal Project: NONE Progress payment No. 04 Payment period ending: 09-06-12 TEICHERT CONSTRUCTION P O BOX 1118 STOCKTON CA 95206 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,715,421.79 0.00 2.a. Extra Work 17,643.99 0.00 b. Adjustment Comp. -16,204.74 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,716,861.04 0.00 5. Mobilization 6. Total Work Completed 1,716,861.04 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,716,861.04 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00