Dept. of Trans. PROGRESS Serial No. Contract No. 15-323-09-26 10-0W1904 PROGRESS PAYMENT VOUCHER %complete: %time: 88% 77% Location: Federal Project: 10-SJ-99-22.9/38.8 NHP-P099(579) Progress payment No. 009 Payment period ending: 11-20-15 A. TEICHERT & SON, INC DBA. TEICHERT CONSTRUCTION 265 VAL DERVIN PARKWAY STOCKTON CA 95206 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 17,724,407.13 1,185,638.05 2. a. Extra Work 434,712.41 70,872.51 b. Adustment Comp. -1,945,058.50 -123,681.89 3. Materials on Hand 4. Earned Subject to Retention 16,214,061.04 1,132,828.67 5. Mobilization 2,166,070.00 0.00 6. Total Work Completed 18,380,131.04 7. Deductions -9,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 18,371,131.04 1,127,828.67 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,127,828.67