Dept. of Trans. FINAL Serial No. Contract No. 17-039-13-15 10-0W5604 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 10-SJ-12-5.1/11.0 NHP-P012(119) Progress payment No. 013 Payment period ending: 02-25-16 GEORGE REED INC 140 EMPIRE AVENUE MODESTO CA 95354 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,778,869.84 -51,681.00 2. a. Extra Work 137,220.18 0.00 b. Adustment Comp. 103,881.54 0.00 3. Materials on Hand 4. Earned Subject to Retention 6,019,971.56 -51,681.00 5. Mobilization 520,000.00 0.00 6. Total Work Completed 6,539,971.56 7. Deductions -12,660.00 85,050.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 6,527,311.56 33,369.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 33,369.00