Dept. of Trans. PROGRESS Serial No. Contract No. 21-172-08-50 10-0W6204 PROGRESS PAYMENT VOUCHER %complete: %time: 81% 41% Location: Federal Project: 10-MER-5-0.7/0.7 ACIM-005-5(153) Progress payment No. 015 Payment period ending: 06-20-21 MDS ENGINEERING & CONSTRUCTION INC 14771 WONDERLAND BLVD REDDING CA 96003 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,058,175.68 139,311.53 2. a. Extra Work 15,860.56 0.00 b. Adustment Comp. 3. Materials on Hand 94,807.10 0.00 4. Earned Subject to Retention 3,168,843.34 139,311.53 5. Mobilization 30,000.00 0.00 6. Total Work Completed 3,104,036.24 7. Deductions -35,000.00 20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,163,843.34 159,311.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 159,311.53