Dept. of Trans. PROGRESS Serial No. Contract No. 20-170-11-50 10-0W6304 PROGRESS PAYMENT VOUCHER %complete: %time: 9% 5% Location: Federal Project: 10-STA-5-27.0/27.4 NONE 10-SJ-5-0.9 Progress payment No. 002 Payment period ending: 06-20-20 RE COM DEVELOPMENT CO 2488 DIXON LN BISHOP CA 93514 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 451,474.65 223,205.84 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 451,474.65 223,205.84 5. Mobilization 6. Total Work Completed 451,474.65 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 451,474.65 223,205.84 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 223,205.84