Dept. of Trans. PROGRESS Serial No. Contract No. 20-204-14-06 10-0W6304 PROGRESS PAYMENT VOUCHER %complete: %time: 16% 2% Location: Federal Project: 10-STA-5-27.0/27.4 NONE 10-SJ-5-0.9 Progress payment No. 003 Payment period ending: 07-20-20 RE COM DEVELOPMENT CO 2488 DIXON LN BISHOP CA 93514 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 764,180.21 312,705.56 2. a. Extra Work 3,771.14 3,771.14 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 767,951.35 316,476.70 5. Mobilization 6. Total Work Completed 767,951.35 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 767,951.35 316,476.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 316,476.70