Dept. of Trans. PROGRESS Serial No. Contract No. 13-325-08-24 10-0W7004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 76% 65% 10-VAR Federal Project: NONE Progress payment No. 03 Payment period ending: 11-20-13 RMP CAPITAL CORP 1747 VETERANS MEMORIAL HWY #6 ISLANDIA NY 117493 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 572,484.41 369,685.19 2.a. Extra Work 74,035.00 74,035.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 646,519.41 443,720.19 5. Mobilization 138,000.00 6,900.00 6. Total Work Completed 784,519.41 7. Deductions -52,149.73 -2,607.49 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 732,369.68 448,012.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 448,012.70