Dept. of Trans. PROGRESS Serial No. Contract No. 15-260-08-42 10-0W8004 PROGRESS PAYMENT VOUCHER %complete: %time: 59% 14% Location: Federal Project: 10-TUO-120-27.4 NONE Progress payment No. 001 Payment period ending: 09-20-15 CCFG CONSTRUCTION 393 MORNING STAR DR SONORA CA 95370 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 158,739.00 158,739.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 158,739.00 158,739.00 5. Mobilization 47,500.00 47,500.00 6. Total Work Completed 206,239.00 7. Deductions -14,430.40 -14,430.40 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 191,808.60 191,808.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 191,808.60