Dept. of Trans. SEMI-FINAL Serial No. Contract No. 22-132-06-59 10-0X3104 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 10-SJ-99-16.8/17.6 NONE Progress payment No. 019 Payment period ending: 01-03-22 BRIDGEWAY CIVIL CONSTRUCTORS INC 3333 VACA VALLEY PKWY #2000 B VACAVILLE CA 95688 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,188,810.98 6,442.75 2. a. Extra Work 578,016.54 144,203.51 b. Adustment Comp. 144,866.00 -77,687.77 3. Materials on Hand 4. Earned Subject to Retention 6,911,693.52 72,958.49 5. Mobilization 686,000.00 0.00 6. Total Work Completed 7,597,693.52 7. Deductions -1,000.00 20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 7,596,693.52 92,958.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 92,958.49