Dept. of Trans. PROGRESS Serial No. Contract No. 15-113-10-08 10-0X3504 PROGRESS PAYMENT VOUCHER %complete: %time: 51% 17% Location: Federal Project: 10-AMA-16-R0.0/R2.5 HSST-000C(383) 10-AMA-88-0.0/3.1 10-TUO-120-7.9/13.2 Progress payment No. 002 Payment period ending: 04-20-15 LINEAR OPTIONS, INC. 792 DURHAM DAYTON HWY. DURHAM CA 95938 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 129,806.11 117,606.11 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 129,806.11 117,606.11 5. Mobilization 6. Total Work Completed 129,806.11 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 129,806.11 117,606.11 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 117,606.11