Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 18-345-11-30 10-0X5604 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 10-STA-99-R18.0/R19.7 ACHS-NHPP-0(996) Progress payment No. 020 Payment period ending: 11-30-18 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077-5085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,208,757.83 0.00 2. a. Extra Work 355,680.12 63,772.43 b. Adustment Comp. 144,855.52 -2,750.94 3. Materials on Hand 4. Earned Subject to Retention 4,709,293.47 61,021.49 5. Mobilization 500,000.00 0.00 6. Total Work Completed 5,209,293.47 7. Deductions -27,000.00 -27,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,182,293.47 34,021.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 34,021.49