Dept. of Trans. PROGRESS Serial No. Contract No. 16-021-13-59 10-0X6104 PROGRESS PAYMENT VOUCHER %complete: %time: 37% 53% Location: Federal Project: 10-MER-5-21.4 IM-005-5(145) E Progress payment No. 003 Payment period ending: 01-20-16 GOLDEN STATE BRIDGE, INC. 3701 MALLARD DRIVE BENICIA CA 945101195 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 517,181.60 39,430.35 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 517,181.60 39,430.35 5. Mobilization 176,700.00 0.00 6. Total Work Completed 693,881.60 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 693,881.60 39,430.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 39,430.35