Dept. of Trans. PROGRESS Serial No. Contract No. 17-054-09-40 10-0X6304 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 24% Location: Federal Project: 10-MER-99-15.1/16.0 NHP-P099 596-E Progress payment No. 007 Payment period ending: 02-20-17 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,055,198.82 4,614.00 2. a. Extra Work 190,981.96 -2,161.25 b. Adustment Comp. 61,044.58 14,418.18 3. Materials on Hand 4. Earned Subject to Retention 1,307,225.36 16,870.93 5. Mobilization 133,300.00 0.00 6. Total Work Completed 1,440,525.36 7. Deductions -19,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,421,525.36 6,870.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,870.93