Dept. of Trans. PROGRESS Serial No. Contract No. 17-170-15-27 10-0X6404 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 63% Location: Federal Project: 10-SJ-99-18.5/20.8 ACNH-PP09-9(600) 10-SJ-99-29.3/33.7 Progress payment No. 007 Payment period ending: 06-20-17 BRIDGEWAY CIVIL CONSTRUCTORS INC 4950 ALLISON PKWY #A VACAVILLE CA 95688 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,163,498.62 92,522.90 2. a. Extra Work 220,844.80 169,845.43 b. Adustment Comp. 10,948.90 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,395,292.32 262,368.33 5. Mobilization 130,000.00 0.00 6. Total Work Completed 1,525,292.32 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,525,292.32 262,368.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 262,368.33