Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 17-237-14-28 10-0X6404 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 10-SJ-99-18.5/20.8 ACNH-PP09-9(600) 10-SJ-99-29.3/33.7 Progress payment No. 009 Payment period ending: 08-09-17 BRIDGEWAY CIVIL CONSTRUCTORS INC 4950 ALLISON PKWY #A VACAVILLE CA 95688 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,207,689.82 9,448.40 2. a. Extra Work 287,525.46 0.00 b. Adustment Comp. 9,400.90 -1,548.00 3. Materials on Hand 4. Earned Subject to Retention 1,504,616.18 7,900.40 5. Mobilization 130,000.00 0.00 6. Total Work Completed 1,634,616.18 7. Deductions -32,450.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,602,166.18 2,900.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,900.40