Dept. of Trans. PROGRESS Serial No. Contract No. 20-055-11-04 10-0X7104 PROGRESS PAYMENT VOUCHER %complete: %time: 25% 39% Location: Federal Project: 10-SJ-99-5.4/6.2 ACNH-X077(27) 10-SJ-120-R2.6/T7.2 Progress payment No. 004 Payment period ending: 02-20-20 PACIFIC INFRASTRUCTURE CONSTRUCTION LLC 871 COTTING CT #A VACAVILLE CA 95688 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 500,748.95 187,930.25 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 0.00 -22,539.39 4. Earned Subject to Retention 500,748.95 165,390.86 5. Mobilization 207,750.00 0.00 6. Total Work Completed 708,498.95 7. Deductions -21,972.25 -19,600.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 686,526.70 145,790.86 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 145,790.86